Text Size:   A+ A- A    •
ODOT Logo


JTA Home > Region 2 JTA Home > I-5 at Beltline

Project News

New off-ramp and signal scheduled for I-5/Beltline interchange ODOT Press Release - June 6, 2013

EUGENE/SPRINGFIELD— Construction on a project to improve the Interstate 5/OR 569 (Randy Papé Beltline) interchange in Eugene/Springfield, will result in a significant traffic control change next week for one of the most heavily traveled interchanges in Lane County. While certain elements will be temporary, the major portion of the traffic control change will be permanent.

(more)
Construction activity begins for next phase of I-5/Beltline improvements in Eugene/Springfield ODOT Press Release - March 25, 2013

EUGENE/SPRINGFIELD— The next phase of improvements for the Interstate 5/Randy Papé Beltline (OR 569) interchange will begin this week as a contractor for ODOT begins placing traffic control signs in the area. Construction will begin the week of April 1.

(more)

Overview

Beltline Units 3-4 Handout (pdf, 2.7 MB)

Beltline Units 3-4 Handout (pdf, 2.7 MB

The Interstate 5 at Randy Papé Beltline, Units 3-7 project is located in Lane County, in the cities of Eugene and Springfield, at the intersection of Interstate 5, mile post 195.45 and Randy Papé Beltline (OR 569). The phased project will correct deficiencies to enable the interchange to safely accommodate travel demands 20 years into the future. The HB 2001 project is being accomplished by two separate projects: I-5 @ Beltline - Unit 3 and I-5 @ Beltline - Unit 4.

The modernization project has been divided into smaller sections (units) to make it easier to construct parts of the project as funding becomes available. Unit 1 was completed in late 2009, and Unit 2 was completed in the Summer of 2011. Units 5, 6 and 7 have been integrated within Units 3 and 4 for construction in 2013 and 2015, respectively. Construction for Unit 3 is well underway, as is design for Unit 4. Unit 3 was awarded to K & E Excavating Inc. on January 30, 2013.

Improvements under contruction in Unit 3 are:

  1. A new I-5 southbound to westbound Beltline off-ramp.
  2. A new I-5 southbound to eastbound Beltline off-ramp.
  3. A new westbound Beltline to southbound I-5 on-ramp.
  4. A new Beltline Bridge over I-5.
  5. And base construction and structures for a new multi-use path to connect south of the interchange to north of the interchange. Path is to open upon completion of Unit 4 in 2016.

The planned improvements being proposed for Unit 4 are:

  1. A new eastbound Beltline auxiliary lane from Coburg Road to southbound I-5 on ramp;
  2. A new southbound I-5 auxiliary lane from Beltline Hwy to I-105;
  3. A new eastbound Beltline to northbound I-5 on-ramp, including a structure over I-5
  4. A new Harlow Bridge (replacement)
  5. Final stages of the Multi Use path that will be partially constructed in Unit 3
  6. A soundwall south of Beltline and east of Coburg Road
  7. A soundwall west of I-5, south of Harlow Road and north of I-105
  8. Noise studies for the replacement of the Harlow Bridge and noise mitigation as warranted

Benefits

The additional work to be done in Units 3 and 4 will continue to modernize the interchange, which serves interstate, regional, and local traffic to the surrounding residential and commercial centers. The units will continue to correct deficiencies to enable the interchange to safely accommodate travel demands 20 years into the future.

The interchange is located at the northern boundary of Oregon’s second largest metropolitan center. Originally constructed in 1968, where dairy farms and pastures once occupied much of the area, today the land is being developed for residential, retail commercial use, interstate traveler services and industrial centers providing regional employment. The once rural interchange cannot accommodate the increase in traffic, creating congestion, delays and safety problems.

Current Status

I-5 @ Beltline Unit 3 was awarded to K & E Excavating Inc. in January and is currently under construction. It is programmed to be completed in late 2014. Construction for Unit 4 is expected to begin in 2015, upon the completion of Unit 3. In January, 2014, a Value Engineering (VE) study was completed resulting in some cost saving recommendations that are now being evaluated and considered by the project development team. At the request of elected state representatives, and in the spirit of the JTA's emphasis on Practical Design, ODOT conducted a Value Engineering study of Unit 4 to reevaluate the design elements for cost savings and reduced impacts on right of way and utilities. To learn the results of the study, click here.

Funding Sources

I-5 @ Beltline Interchange-Unit 3 (Eugene/Sprinfield)

Cumulative Expenditures

I-5 @ Beltline Interchange-Unit 3 (Eugene/Sprinfield)





Project Schedule

I-5 @ Beltline Interchange-Unit 3 (Eugene/Sprinfield)

Project
Initiation

Right of Way
Acquisition Start

Estimated
Construction Start

Estimated
Construction End

May 1, 2010 Oct. 7, 2011 2013 Winter 2014/2015